Product Code Database
Example Keywords: modern warfare -simulation $28-156
barcode-scavenger
   » » Wiki: Gasworks Tunnel
Tag Wiki 'Gasworks Tunnel'.
Tag

Gasworks Tunnel
 (

Rank: 100%
Bluestar Bluestar Bluestar Bluestar Blackstar

The Gasworks Tunnel, also historically known as the Maiden Lane Tunnel,

(2025). 9780300096538, Yale University Press. .
(2025). 9781473822368, Pen and Sword Books. .
is a railway tunnel immediately to the north of King's Cross railway station in London, United Kingdom. It consists of three parallel bores that carry the six tracks of the East Coast Main Line under the Regent's Canal, as well as roads and housing. Each bore is in length and all the tracks are designed to be used bi-directionally.

Each bore was opened separately between 1852 and 1892. In 1977, as part of greater modernisation efforts, the eastern bore was taken out of use and the other two bores were converted to be used bi-directionally. To increase capacity, the eastern bore was reinstated in 2021 as part of a larger upgrade of the station and the entire East Coast Main Line.


Design
The tunnel consists of three parallel bores, officially named the East Bore, Centre Bore, and West Bore. These carry lines A–F respectively and are all in length and are situated to from London King's Cross railway station, where mileage on the East Coast Main Line is measured from. The tunnels are simple in nature, with circular portals decorated with a and .

The proximity of the tunnels to King's Cross prevents the platforms being lengthened and thus prevents longer trains being used on the East Coast Main Line.

(2025). 9781472940025, Bloomsbury Publishing. .
An additional challenge is presented by the strong gradient, with a descent of into the tunnel, before ascending at a rate of towards the northern portal; despite this, it was claimed on many documents to in fact be level.

The speed limit in all the tunnels is towards King's Cross and away from King's Cross. All six lines are designed to be used bi-directionally, and all three bores contain points, with the East and Central bores containing a and the West and Central bores containing a . These points must be used by trains to allow bi-directional access to all platforms except 2, 5, and 7.


History

19th Century
The first of the multiple tunnels was built as part of the construction of the Great Northern Railway between 1851 and 1852, and was built to carry the railway below the Regent's Canal.
(2025). 9781782830252, . .
The original tunnel is now the middle of three parallel bores. A second tunnel to the east was built in 1878, and a third one to the west in 1892. The tunnel's construction was particularly challenging due to the steep gradient and narrow clearances of the railway. The tunnel was named after the Imperial Gas Light and Coke Company, which had a gasworks to the south of Regents Canal near the railway.

On 29 December 1893, a passenger train travelling from King's Cross to Hatfield collided with seven empty coaches that were being shunted into the station to be used in an express service. In his report to the Board of Trade on the accident, railway engineer Horatio Arthur Yorke concluded that it was caused by an unexplained derailment of goods coaches, but that it was exacerbated by poor arrangements for shunting through the tunnels, which he called "hardly satisfactory".


20th Century
On 10 December 1900, an express train travelling from Leeds to King's Cross became stuck in the tunnel due to rail slip, which then delayed other trains. The train managed to restart itself without external intervention. During World War II, some express services ran by the London and North Eastern Railway were so long that they stretched into the Gasworks Tunnel when the locomotive stopped at the buffers at King's Cross, including trains of more than twenty cars.
(2025). 9781445632834, Amberley Publishing Limited. .

On 4 February 1945, the King's Cross railway accident occurred when a heavy train of 17 coaches weighing approximately hauled by a Class A4 locomotive was unable to achieve the climb through the tunnel, slipped to a standstill and rolled back into the station, killing two passengers and injuring 25 others.

In 1977, the eastern bore was taken out of use and the track bed removed. The closure formed part of the remodelling and rationalisation of the station, and other works included a completely new layout between the tunnels and the platforms, the introduction of bi-directional working in the tunnels, and works to improve headroom at the southern end of the tunnels.

As part of its modernisation program, British Rail also began segregating trains by concentrating the suburban services in the western bore and long-distance services in the central bore.

(2025). 9780711029347, Ian Allan Publishing.
At the time of the eastern bore's closure, it had only ever been used by steam trains, and this had caused significant build-up in the tunnel which had to be removed during its renovation and reinstatement.


21st Century
As part of a larger modernisation program of London Kings Cross and the East Coast Main Line, the Eastern bore of the tunnel was reopened. Works began in August 2019 when 11,000 tonnes of spoil were removed from the tunnel before a new track bed was installed. The reopened bore meant that the number of tracks before the station throat increased from four to six, and this allowed for a 50% increase in capacity at King's Cross.

Because the tunnel sits below residential property, the track bed was built with elastic mats that soaked up vibrations. The works were made more difficult by the presence of third-party construction including above the tunnel, as well as the age and conditions within the tunnel. The inside of the tunnel was noisy and dusty with low visibility and mobile phone signal, which all presented extra challenges to contractors.

During a six day closure of platforms 0–6 at Kings Cross railway station on 25–30 December 2020, the throat of King's Cross station was redesigned to incorporate the reopening of the Eastern bore. Overhead line equipment was added to the Eastern bore during this closure, as well as new signalling and waterproofing for the tunnel. Platform zero was rebuilt to align with the bore, with services originally planned to start on 7 June 2021. The first LNER train passed through the tunnel at 07:01 on 26 April 2025, before arriving into the newly built platform zero.

In January 2024, the Gasworks Tunnel and the neighbouring Copenhagen Tunnel became the first in the country to have new signal-boosting technology fitted inside. This stops devices from losing signal and allows passengers to continue calls while travelling through the tunnels. The upgrade was funded entirely by London North Eastern Railway.


See also

Page 1 of 1
1
Page 1 of 1
1

Account

Social:
Pages:  ..   .. 
Items:  .. 

Navigation

General: Atom Feed Atom Feed  .. 
Help:  ..   .. 
Category:  ..   .. 
Media:  ..   .. 
Posts:  ..   ..   .. 

Statistics

Page:  .. 
Summary:  .. 
1 Tags
10/10 Page Rank
5 Page Refs
2s Time